Suspended timber floors with limited inspection access

What an issued Level 3 report in Stockport recorded, with the inspection photograph and the original advice.

EXAMPLE / 04 FLOORS

Lifted floorboards at a bathroom entrance

The report recommended refixing the loose boards and investigating the concealed floor timbers.

Lifted floorboards at a bathroom entrance reveal a narrow view of pipes and debris beneath.Enlarge photograph
THE ORIGINAL PHOTOGRAPH

Exposed pipework and debris beneath lifted floorboards at a bathroom entrance.

ANONYMISED REPORT SUMMARY
Level 3 / 6d · Floors

2
01What was observed
Boards were already lifted at the bathroom entrance, with loose boards and debris beneath. No signs of rot or wood-boring insect attack were seen in the timbers visible through that opening. The ground-floor joists were wholly concealed.
02What the report concluded
The visible timbers could be examined only through one opening. A noticeable first-floor slope was also recorded, with its cause unresolved.
03What remained uncertain
The floor voids were not inspected and no ground-floor access hatch was noted. The ground-floor joists remained concealed, and the assumed suspended timber construction had not been verified.
04What was recommended
Refix the loose bathroom boards and reinstate the lifted boards with a joiner. Include concealed timbers and bearings, decay, insect attack and the floor slope in the scoped damp and timber investigation. The same element called for a Refurbishment and Demolition asbestos survey before legal commitment, to scope materials that the planned works would disturb.
Why this element was rated 2

Floors were rated 2. Loose boards needed refixing, with further investigation of the concealed timbers and the first-floor slope.

Checked against the issued Level 3 report from Stockport: 6d · Floors; pages 35–36; photograph 49. Reviewed 22 November 2026. Wording is an anonymised summary, rather than a reproduction of the report.

Questions for a follow-up call

  • Which part of the floor void was visible and which timber bearings remained concealed?
  • Can the specialist set out the access needed to investigate the floor slope and concealed timbers?

Use the findings and timeframes in your own report when discussing a different home.

Organise the answers in your report action planner